Work in progress Update on ongoing work on the drinking water system
The Community and its establishment of Water and Sanitation (EEASM) continue the renovation works of the public drinking water network.
For pavement installations at Morne Valois (Accreditation roundabout) and Cripple Gate: work will be carried out overnight from 10 October 2014 on 18, from 4 hours to XNUMX hours morning. Note that some interventions will be done during the Weekend.
The project to rehabilitate the drinking water network between Cul de Sac and Orient Bay will start on Monday 13 October 2014, from 7 hours.
We ask the citizens to respect the signaling and the speed limit put in place for the safety of everything in each one. As in some areas of the site, alternating traffic will be installed.
The Community thanks you for your patience and understanding, this work to improve the living environment of the inhabitants is more than necessary.



Driving license Saint-Martin
Driving license Saint-Martin - 2014-09-30
Available in November At the end of September, Mr. Louis Fleming, Territorial Councilor in charge of Transport, and Mr. Jean Arnell, co-manager of Computech, traveled to Finland to meet with the Finnish company Gemalto, partner of Computech For the production of the new Saint-Martin driver's license. The aim of this trip to Europe was to finalize the latest decisions and validate the specifications of the new license (Plan Assurance ...
Read more
Work on the r
Work on the r - 2014-09-15
A deviation will be established The Saint-Martin Water and Sanitation Establishment (EEASM) is continuing work on the drinking water system between Cripple Gate and the Agrément roundabout. The first part of the works at Cripple Gate has been completed, the second part will now take place at night. A new phase of work will begin on Wednesday 17 September 2014 from 7 hours, between the roundabout of Agrément and Morne Valois, where ...
Read more
D
D - 2014-09-09
Sunday 14 September 2014 The Community of Saint-Martin and the Water and Sanitation Establishment (EEASM) inform the population that work will be carried out on the sewage network, this Sunday 14 September 2014, between 6 hours to 18 hours, Level of the crossroads of the Rue de la République and the Boulevard de France (in front of La Vie en Rose). This work will lead to the closing of the crossroads and the implementation of a diversion by the Rue de la Liberté for motorists arriving from Rue de la Liberté.
Read more
Interruption of road traffic on rue de Hollande
Interruption of road traffic on rue de Hollande - 2014-08-25
Works on the sewerage network Works on the sewerage network: interruption of road traffic Rue de Hollande The President of the Territorial Council of Saint-Martin, Mrs. Aline Hanson, and Mr. Louis Fleming, President of the Water and Sanitation Plant of Saint-Martin (EEASM), inform you that in the context of the sanitation rehabilitation program initiated by the Collectivité de Saint-Martin, the rue de Hollande will be closed at the intersection ...
Read more
R
R - 2014-08-21
Rehabilitation of a road in Orléans District Rehabilitation of the road network Rehabilitation of a road in Orléans District The Sustainable Development Pole of the Community of Saint-Martin, led by the 1er Vice President Guillaume Arnell, continues its program of rehabilitation of the road network. After the repair of six busy highways in the first half of 2014, Kennedy Street and St ...
Read more
R
R - 2014-07-28
The Community will proceed by phase, COMMUNIQUE Within the framework of the program of remodeling of the public cemeteries of Saint Martin, the Collective will proceed by phase, with the identification of the graves and the family vaults. The first phase of identification will concern the Marigot Cemetery from Tuesday 15 July 2014 to 29 August 2014. All the people who buried one or more dead in the cemetery of Marigot are invited to ...
Read more
R
R - 2014-04-23
At the beginning of 2e, the Saint-Martin Collective has started repairing six heavily used road axes. Road rehabilitation: Six roads renovated by the Collectivité The Saint-Martin Collectivité has engaged in the beginning of 2014e semester 2 the repair of six heavily used roads; driven by the sustainable development pole of the 2014er vice-president Guillaume Arnell, these works are today ...
Read more
Renovation of roads
Renovation of roads - 2014-04-14
The Community renovates your roads! Marigot, the 15 April 2014 CABINET OF THE PRESIDENT DIRECTORATE OF COMMUNICATION Subject: press release The Community is renovating your roads! Here is the schedule of asphalt works planned on the roads of Saint-Martin in April 2014: Saint-Louis: Planing Thursday 10 April, partial access to traffic from 20 hours. Shanty Town: Laying of mixes Thursday 10 and Friday 11 April. Closed Road from 20 ...