Declaration of completion and conformity of works (DAACT)

Find here the information and the procedure to follow for the declaration of completion and conformity of works (DAACT).

Last updated November 05, 2026

Presentation of the procedure

The declaration of completion and conformity of works (DAACT) is the formality by which the holder of a building permit, a development permit, or a prior declaration certifies that the works are completed and conform to the authorization obtained. It is essential for obtaining the certificate of conformity and for certain subsequent procedures (connections, notarial deeds).

Who is this approach aimed at?

• Any holder of a building permit, development permit or prior declaration who has completed their work

• The agent or architect acting on behalf of the holder

In what cases is this procedure required?

The DAACT (Declaration Attesting Completion of Works) must be submitted as soon as the authorized works are fully completed. It cannot be submitted if the works are only partially completed, except for phases of work that are the subject of a separate authorization.

What is the timeframe for the procedure?

Administrative formalities: there is no processing time for registration. The department then has 3 months (5 months for certain public access buildings or high-rise buildings) to carry out a compliance inspection. If no objection is raised within this period, compliance is considered granted.

How do I carry out this process?

Monitoring and validity of the authorization

The DAACT (Declaration Attesting Completion and Conformity) concludes the administrative processing of the permit. Keep all documents (initial authorization, DOC (Declaration of Completion and Conformity), DAACT, and certificate of conformity) in your property's archives; these documents will be required in the event of a sale, refinancing, or subsequent work.