Planning permission

Find here the information and the procedure to follow to obtain a planning permit.

Last updated November 05, 2026

Presentation of the procedure

A development permit authorizes operations that substantially modify the soil, topography, or appearance of a plot of land: housing developments, campsite development, creation of sports or leisure facilities, and excavation and filling of soil exceeding certain thresholds. It may or may not include construction and/or demolition.

Who is this approach aimed at?

• Land developers, subdividers, promoters

• Local authorities and public institutions for the development of spaces

• Private individuals for earthworks or land division projects subject to a permit

In what cases is this procedure required?

Mandatory in particular for: the creation of a subdivision of more than 2 lots with roads, excavations and earthworks of more than 2 m in height over an area greater than 100 m², the creation of a campsite with more than 20 pitches or a residential leisure park.

What is the timeframe for the procedure?

3 months from the date of submission of the complete file (may be extended to 4 or 5 months depending on the nature of the project and the consultations required).

How to submit your application?

Monitoring and validity of the authorization

The planning permit is valid for 3 years. Work must begin within this period. For a housing development, the lot owners have guarantees linked to the development regulations for a period of 10 years.