Find here the information and procedure to follow to obtain a building permit for a detached house in Saint-Martin.
In this page
Presentation of the procedure
Who is this approach aimed at?
In what cases is this procedure required?
What is the timeframe for the procedure?
How to submit your application?
Monitoring and validity of the authorization
Building permit for a detached house (PCMI) - Cerfa form 13409-16
Additional information sheet / other applicants
Help sheet for calculating floor area
Declaration of commencement of works
Declaration of completion of works
Presentation of the procedure
A building permit for a detached house (PCMI) is a planning permission specifically for individuals wishing to build their primary or secondary residence, as well as its outbuildings (garage, swimming pool, pool house, etc.). It is separate from a standard building permit and uses a dedicated, generally more user-friendly form.
Who is this approach aimed at?
• Private individuals who own land and wish to build or extend their house
• Natural persons, including those engaged in self-construction
• Agents acting on behalf of a private individual (architect, project manager)
In what cases is this procedure required?
Mandatory for all new single-family home construction, regardless of size, and for any extension creating a floor area or footprint exceeding 40 m² in urban areas of the PADSM (20 m² outside these areas). The services of an architect are mandatory if the floor area exceeds 150 m².
What is the timeframe for the procedure?
2 months from receipt of the complete file (standard timeframe for a detached house).
How to submit your application?
Monitoring and validity of the authorization
The building permit is valid for three years from the date of issue. Work must begin within this period and cannot be interrupted for more than one year. A one-year extension can be requested twice before the expiry of the validity period.